It's taken me a while to get migrated to Step 16 in the guide but I've managed to remove Exchange from the server after successfully getting onto Office365.
My question is with me starting step 16 - and then completing the 17,18, and 19 without any delays. How quickly do I need to do these four steps - 1 day, 2 days or 4 or more...and why?
Sorry to ask, I'm doing the migration during the evenings when I'm able to concentrate on the process without distractions.
The reason I tell you to complete the migration and continue with 17,18 and 19 is that as soon as you back up the CA and migrate it and Exchange is uninstalled the SBS is not something that should be used as reliable server anymore. Those steps only take an hour so it should not be a problem to complete them.
Thanks Mariette.